3418 S MOTOR AVE 90034

Certificate Information: 3418 S MOTOR AVE 90034

Application / Permit
24010-10000-00188
Plan Check / Job No.
B24LA00864
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 100% PRIVATELY FUNDED 200-UNIT MIXED-USE (APARTMENT, RETAIL AND OFFICE) PROJECT WITHIN THE EXPOSITION TNP SPECIFIC PLAN, WITH AFFORDABLE HOUSING (22 EXTREMELY LOW UNITS) 1 OF 3
Permit Issued
No
Current Status
Quality Review Completed on 2/9/2024

Permit Application Status History

Submitted 1/17/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 JOE VO
Corrections Issued 2/5/2024 JOE VO
Quality Review Completed 2/9/2024 KEN GILL
Building Plans Picked Up 2/14/2024 APPLICANT
Disabled Access Plans Picked Up 3/15/2024 APPLICANT

Permit Application Clearance Information

DAS Clearance Not Cleared 1/27/2024 Department of Building and Safety
Driveway location Not Cleared 1/27/2024 Department of Transportation
Fire Marshal Fire Life Safety Not Cleared 1/27/2024 Los Angeles Fire Department
Green Code Not Cleared 1/27/2024 Department of Building and Safety
Hydrant and Access approval Not Cleared 1/27/2024 Los Angeles Fire Department
Low Impact Development (LID) Not Cleared 1/27/2024 Bureau of Sanitation
Permit Not Cleared 1/27/2024 Bureau of Engineering
Roof/Waste drainage to street Not Cleared 1/27/2024 Bureau of Engineering
Sewer availability Not Cleared 1/27/2024 Bureau of Engineering
Specific Plan Not Cleared 1/27/2024 Department of Transportation
Trees in Parkway Not Cleared 1/27/2024 Bureau of Street Services
Zoning Clearance Not Cleared 1/27/2024 Department of Building and Safety
Frnt yard landscape/Water mgmt Not Cleared 2/5/2024 City Planning Department
Miscellaneous Not Cleared 2/5/2024 Bureau of Engineering
Opn space landscape/Water mgmt Not Cleared 2/5/2024 City Planning Department
SB8 RUD Not Cleared 2/5/2024 Los Angeles Housing Department
Specific Plan Not Cleared 2/5/2024 City Planning Department
ZI Not Cleared 2/5/2024 City Planning Department
ZI Not Cleared 2/5/2024 City Planning Department
Address approval Cleared 2/28/2024 DINAH GARIN
Highway dedication Not Cleared 2/28/2024 Bureau of Engineering
Eng Process Fee Ord 176,300 Cleared 3/1/2024 DINAH GARIN
Bicycle Parking Not Cleared 3/6/2024 Bureau of Engineering
Bicycle Parking Not Cleared 3/6/2024 Department of Transportation
Miscellaneous Cleared 3/13/2024 DALIA MOKAYED
Building over 36-ft Cleared 3/18/2024 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/18/2024 CALOSHA APPROVED
Grading Pre-Inspection Cleared 3/21/2024 JOE VO

Contact Information

No Data Available.

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

No Data Available.