3250 N GLENDALE BLVD 1-9 90039
Certificate Information: 3250 N GLENDALE BLVD 1-9 90039
- Application / Permit
- 24016-10000-05441
- Plan Check / Job No.
- B24LA03006
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- EPLAN Proposed change of use from Bank to multi-tenant retail and one office (total 8 tenants (retail) on ground floor and 1 (office) on mezzanine), scope to also include tenant improvements. "LIMIT THE HOURS OF OPERATION FROM 7am TO 11pm. "
- Permit Issued
- Issued on 11/11/2024
- Issuing Office
- Current Status
- Issued on 11/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 2/21/2024 | APPLICANT |
Assigned to Plan Check Engineer | 2/22/2024 | MICHAEL LOPEZ |
Corrections Issued | 3/7/2024 | MICHAEL LOPEZ |
Quality Review Completed | 3/12/2024 | GARO TELMI |
Applicant returned to address corrections | 7/18/2024 | MICHAEL LOPEZ |
Applicant returned to address corrections | 8/21/2024 | MICHAEL LOPEZ |
Plan Check Approved | 11/8/2024 | MICHAEL LOPEZ |
Issued | 11/11/2024 | APPLICANT |
Permit Application Clearance Information
"Q" conditions | Cleared | 4/10/2024 | SPENCER WEJROWSKI |
Comm Cor/Mini-Mall | Cleared | 4/10/2024 | SPENCER WEJROWSKI |
ZI | Cleared | 4/10/2024 | SPENCER WEJROWSKI |
Address approval | Cleared | 4/11/2024 | TREVOR QUAN |
Sewer availability | Cleared | 4/11/2024 | TREVOR QUAN |
Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | TREVOR QUAN |
Green Code | Cleared | 4/18/2024 | Sergio Muniz |
DAS Clearance | Cleared | 4/19/2024 | Sergio Muniz |
Permit | Cleared | 4/24/2024 | TREVOR QUAN |
Encroachment in public way | Cleared | 5/13/2024 | MARK REYES |
Zoning Plan Check | Cleared | 6/6/2024 | Sergio Muniz |
Trees in Parkway | Cleared | 6/20/2024 | ADALBERTO VERA |
ZI | Cleared | 7/3/2024 | LINDA LOU |
Low Impact Development (LID) | Cleared | 11/6/2024 | ERNEST TSE |
Contact Information
Architect | Malak,, Hany; Lic. No.: NA27490 | , |
Contractor | ; Lic. No.: 865616-B | , |
Engineer | Fitzgerald,, Shane Scott; Lic. No.: S4757 | 950 S GRAND AVE 4TH FL LOS ANGELES, CA 90015 |
Inspector Information
JULIAN CAPUCETTI, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 12/20/2024 | Approved | RAMAZANALI ALMASI |
Footing/Foundation/Slab | 1/7/2025 | Partial Approval | RAMAZANALI ALMASI |
Pre-Inspection | 3/19/2025 | Partial Approval | PAUL BAZERKANIAN |
Excavation/Setback/Form/Re-Bar | 3/20/2025 | Pending Review | |
Special/Order Compliance | 3/20/2025 | Corrections Issued | PAUL BAZERKANIAN |
Wood Frame | 3/24/2025 | Partial Approval | RAFAEL CORTES |
Pre-Inspection | 3/26/2025 | Partial Approval | RAFAEL CORTES |
Grading Pre-Inspection | 4/15/2025 | Partial Approval | RONALD JIMENEZ |
Light Gage Steel Frame | 4/15/2025 | Not Ready for Inspection | RONALD JIMENEZ |
Special/Order Compliance | 4/15/2025 | Not Ready for Inspection | RONALD JIMENEZ |
Wood Frame | 4/21/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |