10450 W DUNLEER DR 90064

Certificate Information: 10450 W DUNLEER DR 90064

Application / Permit
16010-20000-01780
Plan Check / Job No.
B16VN05847
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREG SHAPED 81'-4" X 35'-7" FULLY SPRINKLERED TWO STORY SINGLE FAMILY DWELLING W/ ATTACHED GARAGE.
Permit Issued
Issued on 11/1/2017
Issuing Office
Valley
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2016 APPLICANT
Assigned to Plan Check Engineer 6/2/2016 JEROME MAGAT PALMA
Corrections Issued 6/3/2016 JEROME MAGAT PALMA
Quality Review Completed 6/13/2016 STEVEN KIM
Building Plans Picked Up 6/15/2016 APPLICANT
Green Plans Picked Up 6/16/2016 APPLICANT
Applicant returned to address corrections 10/26/2017 JEROME MAGAT PALMA
Plan Check Approved 11/1/2017 JEROME MAGAT PALMA
Issued 11/1/2017 LADBS
CofO in Progress 2/7/2023 RICHARD STEINBACH
Permit Finaled 2/8/2023 DANIEL ORRANTE
CofO Issued 2/8/2023 DANIEL ORRANTE
Permit Finaled 2/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/13/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 10/13/2017 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 10/13/2017 JOHN CONNEALLY
Low Impact Development Cleared 10/13/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/13/2017 NAZILA NOORIFAR
Sewer availability Cleared 10/13/2017 ADRIAN SANCHEZ
Green Code Cleared 10/25/2017 ROLLIN GETTLE III

Contact Information

Architect Woodcraft, Lawrence Albert; Lic. No.: C23651 20242 ELKWOOD STREET      WINNETKA, CA 91306
Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2018 Partial Approval DAVID HEINE
Excavation/Setback/Form/Re-Bar 7/18/2018 Partial Approval DAVID HEINE
PLUMBING-Rough 7/18/2018 Partial Approval DAVID HEINE
Sewer 7/18/2018 Partial Approval DAVID HEINE
Underground Mechanical 7/18/2018 Partial Approval DAVID HEINE
Footing/Foundation/Slab 8/1/2018 Partial Approval DAVID HEINE
Footing/Foundation/Slab 8/9/2018 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 8/20/2018 Partial Approval ANDREW NAVE
Gas Test 10/4/2018 Approved DAVID HEINE
PLUMBING-Rough 10/4/2018 Approved DAVID HEINE
HVAC-Rough 10/10/2018 Approved DAVID HEINE
ELECTRICAL-Rough 10/23/2018 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/23/2018 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 11/9/2018 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 11/13/2018 Approved DAVID HEINE
Green Building Rough 11/13/2018 Approved DAVID HEINE
Verify Sprinkler Sign Off 11/13/2018 Approved DAVID HEINE
Interior/Exterior Lathing 11/16/2018 Partial Approval MICHAEL TEMPLE
Insulation 12/12/2018 Approved DAVID HEINE
Shower Pan 12/12/2018 Approved DAVID HEINE
Drywall Nailing 12/21/2018 Approved DAVID HEINE
Interior/Exterior Lathing 1/16/2019 Approved DAVID HEINE
Service/Power Release 4/24/2019 Approved EVAN COOPER
Final 6/7/2019 Corrections Issued RONALD WEBER
Gas Test 6/7/2019 Approved RONALD WEBER
Green Building Final 6/7/2019 Approved RONALD WEBER
SGSOV-Seismic Gas S/O Valve 6/7/2019 SGSOV Approved RONALD WEBER
Smoke Detectors 6/7/2019 Approved RONALD WEBER
Final 8/14/2019 Conditional Approval RONALD WEBER