17310 W VEREDA DE LA MONTURA 90272

Certificate Information: 17310 W VEREDA DE LA MONTURA 90272

Application / Permit
19010-10000-01311
Plan Check / Job No.
B19LA06435
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(10) Home for the Aged with special care
Work Description
NEW PROPOSED RESIDENTIAL CARE FACILITY FOR THE ELDERLY (R2.1 OCCUPANCY) IN A (4)-STORY BUILDING TYPE IB CONSTRUCTION, OVER (2)-LEVELS OF SUBTERRANEAN PARKING TYPE IA CONSTRUCTION IN COMPLIANCE WITH THE CITY OF LOS ANGELES ELDER CARE ORDINANCE. (PER ZA-2017-2170-ELD-CDP-SPR-IA)
Permit Issued
Issued on 7/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2019 APPLICANT
Disabled Access Plans Picked Up 4/11/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 GARO TELMI
Green Plans Picked Up 4/24/2019 APPLICANT
Corrections Issued 5/6/2019 GARO TELMI
Quality Review Completed 5/6/2019 CHAD DOI
Building Plans Picked Up 5/7/2019 APPLICANT
Applicant returned to address corrections 7/16/2019 GARO TELMI
Applicant returned to address corrections 7/25/2019 GARO TELMI
Applicant returned to address corrections 8/2/2019 GARO TELMI
Applicant returned to address corrections 8/9/2019 GARO TELMI
Applicant returned to address corrections 8/15/2019 GARO TELMI
Applicant returned to address corrections 10/7/2019 GARO TELMI
Applicant returned to address corrections 10/18/2019 GARO TELMI
Applicant returned to address corrections 10/25/2019 GARO TELMI
Applicant returned to address corrections 11/14/2019 GARO TELMI
Applicant returned to address corrections 11/26/2019 GARO TELMI
Applicant returned to address corrections 1/9/2020 GARO TELMI
Applicant returned to address corrections 1/14/2020 GARO TELMI
Applicant returned to address corrections 1/29/2020 GARO TELMI
Applicant returned to address corrections 3/2/2020 GARO TELMI
Plan Check Approved 6/25/2020 GARO TELMI
Issued 7/9/2020 APPLICANT
CofO in Progress 11/14/2023 DERRICK SPENCER
Permit Finaled 11/14/2023 HENRY BAGHDASSARIAN
CofO Issued 11/14/2023 HENRY BAGHDASSARIAN
Permit Finaled 11/14/2023 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/16/2019 GILBERT URREA
Driveway location Cleared 9/4/2019 VALERIA CEJA
Internal circulation Cleared 9/4/2019 VALERIA CEJA
Bicycle Parking Cleared 9/6/2019 JAMES KHO
Encroachment in public way Cleared 9/6/2019 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 9/6/2019 JAMES KHO
Comm Cor/Mini-Mall Cleared 9/18/2019 DAISY BENICIA
Comm Cor/Mini-Mall Cleared 9/18/2019 DAISY BENICIA
Tract Map conditions Cleared 9/18/2019 DAISY BENICIA
ZA Case Cleared 9/18/2019 DAISY BENICIA
ZA Case Cleared 9/18/2019 DAISY BENICIA
ZA Case Cleared 9/18/2019 DAISY BENICIA
Coastal Zone Cleared 9/30/2019 DAISY BENICIA
Frnt yard landscape/Water mgmt Cleared 9/30/2019 DAISY BENICIA
Site Plan review Cleared 9/30/2019 DAISY BENICIA
ZA Case Cleared 9/30/2019 DAISY BENICIA
Green Code Cleared 10/2/2019 NEGAR NEJAD
Landscape for retaining wall Cleared 10/4/2019 DAISY BENICIA
Building over 3-story or 36-ft Cleared 11/26/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/26/2019 CALOSHA APPROVED
Highway dedication Cleared 1/6/2020 NIKTA MOUSAVI
GPI Written Notices Cleared 1/9/2020 GRANT WOODS
Grading Pre-Inspection Cleared 1/9/2020 GRANT WOODS
Food Service Establishment Cleared 1/15/2020 KENNETH BROWNE
Address approval Cleared 1/16/2020 ELENA LOPEZ
Trees in Parkway Cleared 1/17/2020 JOHN KIM
Food establishment approval Cleared 1/29/2020 LACDHS APPROVED
Disturb/Remove Protected Trees Cleared 1/30/2020 STEPHEN DUPREY
Work Adjacent to Public Way Cleared 2/14/2020 DINAH GARIN
Fire Marshall Fire Life Safety Cleared 2/19/2020 DOMINIQUE MEDINA
DAS Clearance Cleared 2/20/2020 WAI LAU
Permit Cleared 4/28/2020 DINAH GARIN
Miscellaneous Cleared 5/5/2020 NIKTA MOUSAVI
Sewer availability Cleared 5/5/2020 ANTHONY MAINEZ
Low Impact Development Cleared 5/20/2020 MARTIN FRAGOSO
Stormwater Pollution Mitigatn Cleared 5/20/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/29/2020 ANTHONY MAINEZ

Contact Information

Architect Moses,, Jacob; Lic. No.: C15827 11878 LA GRANGE AVE      LOS ANGELES, CA 90025
Contractor Owner-Builder       ,
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Faghihi,, Mahmoud; Lic. No.: S5789 888 S FIGUEROA STREET 18TH FLOOR      LOS ANGELES, CA 90017
Engineer Goodman,, Harvey Allan; Lic. No.: C15900 834 17TH STREET      SANTA MONICA, CA 90403
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Spindler,, Ronald W; Lic. No.: C13194 16823 SATICOY STREET      VAN NUYS, CA 91406

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/24/2020 Approved ALAN NOVAK
Special/Order Compliance 8/7/2020 Approved JOHN DODGE
Piling/Pier/Caisson 11/23/2020 Partial Inspection JOHN DODGE
Piling/Pier/Caisson 11/30/2020 Partial Approval TED RIES
Piling/Pier/Caisson 12/1/2020 Partial Inspection JOHN DODGE
Special/Order Compliance 12/8/2020 Approved JOHN DODGE
Pre-Inspection 12/10/2020 Approved JOHN DODGE
Piling/Pier/Caisson 12/15/2020 Partial Inspection JOHN DODGE
Deputy Reinf. Concrete 3/8/2021 Conditional Approval TED RIES
Green Building Rough 3/8/2021 Not Ready for Inspection DERRICK SPENCER
Pre-Inspection 3/8/2021 Approved DERRICK SPENCER
Reinforced Concrete Frame 3/8/2021 Partial Approval DERRICK SPENCER
Verify Sprinkler Sign Off 3/8/2021 Approved DERRICK SPENCER
Deputy Shotcrete 3/9/2021 Approved DERRICK SPENCER
SWPPP-Const. Storm Water 3/15/2021 Completed DERRICK SPENCER
SUSMP-Std. Urban Storm Water 3/18/2021 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/22/2021 Partial Approval DERRICK SPENCER
Pre-Inspection 3/23/2021 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/25/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 3/26/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/30/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/1/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/13/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/14/2021 Approved DERRICK SPENCER
Deputy Shotcrete 4/14/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/15/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 4/15/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/16/2021 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/16/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 4/21/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/22/2021 Partial Approval DERRICK SPENCER
Green Building Rough 4/23/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 4/23/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 4/27/2021 Partial Approval DERRICK SPENCER
Green Building Rough 4/28/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 4/28/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/29/2021 Approved DERRICK SPENCER
Piling/Pier/Caisson 4/29/2021 Partial Approval DERRICK SPENCER
Green Building Rough 4/30/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 4/30/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 5/4/2021 Partial Approval DERRICK SPENCER
Green Building Rough 5/5/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 5/5/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/6/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 5/6/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 5/17/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 5/18/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 5/20/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 5/21/2021 Partial Approval DERRICK SPENCER
SWPPP-Const. Storm Water 5/21/2021 Completed DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 5/25/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/26/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 5/27/2021 Approved DERRICK SPENCER
Green Building Rough 5/28/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 5/28/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/1/2021 Approved DERRICK SPENCER
Reinforced Masonry Frame 6/1/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/2/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 6/2/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/3/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/4/2021 Approved DERRICK SPENCER
Green Building Rough 6/7/2021 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 6/7/2021 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 6/9/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 6/14/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/15/2021 Approved DERRICK SPENCER
Green Building Rough 6/15/2021 Approved DERRICK SPENCER
Reinforced Concrete Frame 6/15/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 6/18/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/22/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/23/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 6/24/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 6/28/2021 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 6/29/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/30/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 7/2/2021 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 7/6/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/8/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 7/9/2021 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/12/2021 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 7/13/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 7/14/2021 Approved DERRICK SPENCER
Deputy Shotcrete 7/14/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 7/19/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 7/19/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 7/20/2021 Approved DERRICK SPENCER
Reinforced Concrete Frame 7/20/2021 Partial Approval DERRICK SPENCER
Deputy Shotcrete 7/21/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 7/21/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 7/28/2021 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 7/29/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 8/2/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/4/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/5/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/6/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/9/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/9/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/10/2021 Approved DERRICK SPENCER
Reinforced Concrete Frame 8/10/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/11/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/12/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/13/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 8/16/2021 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/16/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/17/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/18/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/19/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/20/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/23/2021 Approved DERRICK SPENCER
Wood Frame 8/30/2021 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/1/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 9/2/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/3/2021 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Approved DERRICK SPENCER
Light Gage Steel Frame 9/10/2021 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 9/13/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 9/17/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/21/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/22/2021 Approved DERRICK SPENCER
Light Gage Steel Frame 9/28/2021 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 10/1/2021 Approved DERRICK SPENCER
Light Gage Steel Frame 10/4/2021 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 10/12/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 10/13/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/14/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/15/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/18/2021 Conditional Approval GRANT WOODS
Light Gage Steel Frame 10/19/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/22/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/26/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/28/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 10/29/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/1/2021 Approved DERRICK SPENCER
Deputy Shotcrete 11/4/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/4/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/5/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/9/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/17/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/18/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 11/19/2021 Approved DERRICK SPENCER
Deputy Reinf. Masonry 12/6/2021 Approved DERRICK SPENCER
Deputy Reinf. Masonry 12/7/2021 Approved DERRICK SPENCER
Deputy Reinf. Masonry 12/8/2021 Approved DERRICK SPENCER
Deputy Reinf. Masonry 12/9/2021 Approved DERRICK SPENCER
Deputy Reinf. Masonry 12/10/2021 Approved DERRICK SPENCER
Deputy Steel/Welding 12/13/2021 Approved DERRICK SPENCER
Light Gage Steel Frame 12/16/2021 Partial Approval DERRICK SPENCER
Deputy Shotcrete 12/17/2021 Approved DERRICK SPENCER
Deputy Shotcrete 12/20/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 12/21/2021 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 1/3/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Approval DERRICK SPENCER
Structural Steel Frame 1/7/2022 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 1/11/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 1/12/2022 Partial Approval DERRICK SPENCER
Pre-Inspection 1/18/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 1/21/2022 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 1/24/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 1/31/2022 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 2/2/2022 Approved JEFF BYTHEWAY
Light Gage Steel Frame 2/3/2022 Partial Approval DERRICK SPENCER
Deputy Shotcrete 2/4/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 2/4/2022 Partial Approval DERRICK SPENCER
Piling/Pier/Caisson 2/7/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 2/11/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/17/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/18/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/22/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 2/23/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/24/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/2/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 3/2/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 3/8/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/11/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 3/11/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 3/14/2022 Not Ready for Inspection DERRICK SPENCER
Interior/Exterior Lathing 3/15/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/17/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/21/2022 Approved DERRICK SPENCER
Insulation 3/21/2022 Not Ready for Inspection DERRICK SPENCER
Structural Steel Frame 3/21/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 3/22/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/24/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 3/24/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/25/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 3/31/2022 Partial Approval DERRICK SPENCER
Insulation 4/4/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/5/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 4/6/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/7/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/11/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 4/11/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/12/2022 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 4/13/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 4/14/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 4/15/2022 Not Ready for Inspection DERRICK SPENCER
Deputy Steel/Welding 4/19/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 4/19/2022 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 4/20/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 4/20/2022 Approved DERRICK SPENCER
Reinforced Concrete Frame 4/20/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 4/26/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 4/26/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 4/27/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 4/28/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 4/29/2022 Approved DERRICK SPENCER
Reinforced Concrete Frame 4/29/2022 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 5/2/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 5/4/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 5/6/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/13/2022 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 5/20/2022 Approved JEFF BYTHEWAY
Light Gage Steel Frame 5/23/2022 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 5/25/2022 Conditional Approval DERRICK SPENCER
Deputy Drilled-In Anchors 5/26/2022 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 5/27/2022 Conditional Approval DAVID TSAU
Deputy Reinf. Masonry 6/1/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 6/2/2022 Conditional Approval SORIN CIRSTOIU
Light Gage Steel Frame 6/2/2022 Not Ready for Inspection SORIN CIRSTOIU
Deputy Reinf. Masonry 6/3/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 6/7/2022 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/8/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 6/9/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/10/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 6/17/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 6/21/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/22/2022 Approved DERRICK SPENCER
Interior/Exterior Lathing 6/22/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 6/23/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/24/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 6/27/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 6/30/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 7/1/2022 Conditional Approval DERRICK SPENCER
Light Gage Steel Frame 7/6/2022 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 7/14/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 7/19/2022 Approved DERRICK SPENCER
Interior/Exterior Lathing 7/25/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 7/28/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 7/28/2022 Partial Approval DERRICK SPENCER
Structural Steel Frame 8/12/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/30/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/1/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/15/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 9/26/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/30/2022 Partial Approval DERRICK SPENCER
SWPPP-Const. Storm Water 10/3/2022 Completed DERRICK SPENCER
Deputy Steel/Welding 10/24/2022 Approved DERRICK SPENCER
Light Gage Steel Frame 11/1/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 11/4/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 11/10/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 11/17/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 11/22/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 11/30/2022 Partial Approval DERRICK SPENCER
Deputy Shotcrete 12/7/2022 Conditional Approval DERRICK SPENCER
Light Gage Steel Frame 12/7/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 12/8/2022 Partial Approval DERRICK SPENCER
SWPPP-Const. Storm Water 12/12/2022 Completed DERRICK SPENCER
Light Gage Steel Frame 12/13/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 12/22/2022 Corrections Issued SORIN CIRSTOIU
Light Gage Steel Frame 12/27/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 12/30/2022 Approved DERRICK SPENCER
Masonry Wall/Backfill 12/30/2022 Not Ready for Inspection DERRICK SPENCER
Masonry Wall/Backfill 1/3/2023 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 1/9/2023 Approved DERRICK SPENCER
Pre-Inspection 1/10/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 1/18/2023 Conditional Approval DERRICK SPENCER
Light Gage Steel Frame 1/18/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 1/26/2023 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/6/2023 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 2/15/2023 Conditional Approval DERRICK SPENCER
SWPPP-Const. Storm Water 2/24/2023 Completed DERRICK SPENCER
SUSMP-Std. Urban Storm Water 3/1/2023 Approved DERRICK SPENCER
SWPPP-Const. Storm Water 3/13/2023 Completed DERRICK SPENCER
SUSMP-Std. Urban Storm Water 3/15/2023 Approved DERRICK SPENCER
T-Bar Ceiling 3/22/2023 Partial Approval DERRICK SPENCER
Final 3/30/2023 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 3/30/2023 Partial Approval DERRICK SPENCER
Green Building Final 3/30/2023 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 3/30/2023 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved DERRICK SPENCER
Smoke Detectors 3/30/2023 Approved DERRICK SPENCER
Final 6/22/2023 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 6/22/2023 Approved DERRICK SPENCER
Green Building Final 6/22/2023 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 6/28/2023 Approved DERRICK SPENCER
Pre-Inspection 7/13/2023 Corrections Issued DERRICK SPENCER
Final 8/1/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 8/1/2023 Not Ready for Inspection DERRICK SPENCER
Final 8/14/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 8/14/2023 Not Ready for Inspection DERRICK SPENCER
Final 8/28/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 8/28/2023 Not Ready for Inspection DERRICK SPENCER
Final 10/24/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 10/24/2023 Approved DERRICK SPENCER
Final 11/13/2023 Not Ready for Inspection DERRICK SPENCER
Final 11/14/2023 OK to Issue CofO DERRICK SPENCER