19755 1/2 W MALDEN ST 91306
Certificate Information: 19755 1/2 W MALDEN ST 91306
- Application / Permit
- 20010-20000-02361
- Plan Check / Job No.
- B20VN09204
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 43'-0" X 41'-2" IRREGULAR-SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Current Status
- CofO Issued on 9/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 7/14/2020 | APPLICANT |
Assigned to Plan Check Engineer | 7/22/2020 | ROSENDO MEDINA |
Corrections Issued | 7/22/2020 | ROSENDO MEDINA |
Applicant returned to address corrections | 8/26/2021 | ROSENDO MEDINA |
Applicant returned to address corrections | 10/26/2021 | ROSENDO MEDINA |
Building Plans Picked Up | 10/28/2021 | APPLICANT |
Applicant returned to address corrections | 8/4/2022 | JOSEPH RAFOLS |
Plan Check Approved | 9/9/2022 | FERNANDO FLORES |
Issued | 9/9/2022 | APPLICANT |
CofO in Progress | 2/16/2023 | DAVID SCANTLIN |
CofO Issued | 9/19/2023 | JOHN JANSON |
Permit Finaled | 9/19/2023 | JOHN JANSON |
Permit Application Clearance Information
Address approval | Cleared | 10/1/2021 | DAGOVERTO GUERRERO |
Eng Process Fee Ord 176,300 | Cleared | 10/4/2021 | DAGOVERTO GUERRERO |
Sewer availability | Cleared | 10/4/2021 | DAGOVERTO GUERRERO |
Hydrant and Access approval | Cleared | 12/19/2021 | ROBERT DUFF |
Construction near power lines | Cleared | 3/4/2022 | RIDWAN HARDY |
Low Impact Development | Cleared | 8/25/2022 | MARCO SANCHEZ |
Roof/Waste drainage to street | Cleared | 9/6/2022 | JOSE DUARTE-DIAZ |
Public Works-Highway Ded. | Cleared | 9/6/2022 | JOSE DUARTE-DIAZ |
Public Works-Sewers | Cleared | 9/6/2022 | JOSE DUARTE-DIAZ |
Public Works-Open Permits | Cleared | 9/6/2022 | JOSE DUARTE-DIAZ |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
DAVID SCANTLIN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
KRISTEN BEVERIDGE, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 10/13/2022 | Approved | JOHN KIDWELL |
PLUMBING-Rough | 10/13/2022 | Partial Approval | JOHN KIDWELL |
Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Approved | DAVID SCANTLIN |
ELECTRICAL-Rough | 11/28/2022 | Approved | DAVID SCANTLIN |
HVAC-Rough | 11/28/2022 | Approved | DAVID SCANTLIN |
PLUMBING-Rough | 11/28/2022 | Approved | DAVID SCANTLIN |
Wood Frame | 11/28/2022 | Not Ready for Inspection | DAVID SCANTLIN |
Drywall Nailing | 12/7/2022 | Approved | JUSTIN HAWLEY |
Insulation | 12/7/2022 | Approved | JUSTIN HAWLEY |
BUILDING-Rough-Frame | 12/14/2022 | Approved | DAVID SCANTLIN |
Green Building Rough | 12/14/2022 | Approved | DAVID SCANTLIN |
Interior/Exterior Lathing | 12/14/2022 | Partial Approval | DAVID SCANTLIN |
Shower Pan | 12/14/2022 | Approved | DAVID SCANTLIN |
Verify Sprinkler Sign Off | 12/14/2022 | Approved | DAVID SCANTLIN |
Interior/Exterior Lathing | 12/20/2022 | Partial Approval | JOHN KIDWELL |
Pre-Inspection | 12/20/2022 | Partial Inspection | JUSTIN HAWLEY |
Final | 1/31/2023 | Corrections Issued | DAVID SCANTLIN |
Green Building Final | 1/31/2023 | Not Ready for Inspection | DAVID SCANTLIN |
SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Approved | DAVID SCANTLIN |
Service/Power Release | 1/31/2023 | Not Ready for Inspection | DAVID SCANTLIN |
Smoke Detectors | 1/31/2023 | Approved | DAVID SCANTLIN |
Final | 2/15/2023 | OK to Issue CofO | DAVID SCANTLIN |
Green Building Final | 2/15/2023 | Approved | DAVID SCANTLIN |
Service/Power Release | 2/15/2023 | Approved | DAVID SCANTLIN |
Special/Order Compliance | 2/22/2023 | Corrections Issued | DAVID SCANTLIN |
Special/Order Compliance | 9/1/2023 | Approved | DAVID SCANTLIN |
Service/Power Release | 9/19/2023 | Approved | DAVID SCANTLIN |