732 N SYCAMORE AVE 90038
Certificate Information: 732 N SYCAMORE AVE 90038
- Application / Permit
- 20014-20000-03614
- Plan Check / Job No.
- B20VN10993
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSD 32'-2" X 33'-8" IRREGULAR SHAPED 1ST FLOOR AND 2ND FLOOR ADDITION TO (E) SFD. NFPA 13D FIRE SPRINLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | MARVEL DELACRUZ |
| Corrections Issued | 10/1/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 10/6/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Applicant returned to address corrections | 4/26/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/25/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/29/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/1/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 8/29/2022 | RAPHAEL ROSAS |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 5/12/2023 | JOAQUIN GREENOUGH |
| CofO Issued | 5/19/2023 | DEROLD HAUFF |
| Permit Finaled | 5/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 2/3/2022 | MITESH PATEL |
| Sewer availability | Cleared | 2/10/2022 | WALLIE JONG |
| Green Code | Cleared | 4/26/2022 | MARVEL DELACRUZ |
| Roof/Waste drainage to street | Cleared | 8/19/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/29/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/30/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 9/30/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 9/30/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 10/21/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/22/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 12/20/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/30/2022 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/12/2023 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/12/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 1/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/12/2023 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 1/12/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/12/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 1/20/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 1/20/2023 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 1/27/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/27/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/31/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/1/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/3/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/4/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 5/4/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 5/4/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 5/4/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 5/4/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/4/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/11/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 5/11/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| HVAC-Final | 5/11/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 5/11/2023 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/11/2023 | Approved | JOAQUIN GREENOUGH |