2809-2809 1/2 N GRIFFIN AVE 90031

Certificate Information: 2809-2809 1/2 N GRIFFIN AVE 90031

Application / Permit
21016-10000-22322
Plan Check / Job No.
B21LA15864
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT PORTION (E) DUPLEX ON FIRST FLOOR TO ACCESSORY DWELLING UNIT (367 SF) PER ORDINANCE. FIRE SPRINKLER NFPA-13 R THROUGHOUT (BUILDING #2) 1 OF 2
Permit Issued
Issued on 5/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Disabled Access Plans Picked Up 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 FARSHAD ALIMOHAMADI
Corrections Issued 10/20/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 10/21/2021 SAI KHUM
Building Plans Picked Up 10/25/2021 APPLICANT
Applicant returned to address corrections 1/11/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 5/25/2022 FARSHAD ALIMOHAMADI
Issued 5/26/2022 APPLICANT
CofO in Progress 7/11/2023 AMY COLIN
Permit Finaled 7/26/2023 RUBEN SALAS
CofO Issued 7/26/2023 RUBEN SALAS
Permit Finaled 7/26/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/3/2021 WALLIE JONG
Highway dedication Cleared 11/3/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 11/3/2021 WALLIE JONG
Sewer availability Cleared 11/3/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/4/2021 WALLIE JONG
Tenant Habitability Plan Cleared 2/2/2022 ISMAEL HERNANDEZ
DAS Clearance Cleared 3/30/2022 SHINE LIN
HPOZ Cleared 5/25/2022 KATIE DEBIASE

Contact Information

Contractor A T A Construction Inc; Lic. No.: 1044074-B 9109 GREGORY WAY      BEVERLY HILLS, CA 90211
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

AMY COLIN, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
LILIANA PORTILLO, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
DEVON JACKSON, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
KELVIN MARTINEZ, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER MORFIN, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MAGCALAS, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI
GEM DE OCAMPO, (213) 202-3439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/21/2022 Conditional Approval AMY COLIN
Footing/Foundation/Slab 6/23/2022 Approved AMY COLIN
Wood Frame 7/11/2022 Not Ready for Inspection OSVALDO PARAMO
Pre-Inspection 7/15/2022 Corrections Issued OSVALDO PARAMO
Deputy Wood Construction 7/21/2022 No Access for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Not Ready for Inspection AMY COLIN
Wood Frame 7/26/2022 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Approved AMY COLIN
Wood Frame 8/1/2022 Partial Approval AMY COLIN
BUILDING-Rough-Frame 9/7/2022 Partial Approval AMY COLIN
ELECTRICAL-Rough 9/7/2022 Approved AMY COLIN
HVAC-Rough 9/7/2022 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 9/7/2022 Approved AMY COLIN
HVAC-Rough 9/14/2022 Approved AMY COLIN
Interior/Exterior Lathing 9/28/2022 Approved AMY COLIN
Shower Pan 9/28/2022 Approved AMY COLIN
Insulation 10/26/2022 Approved AMY COLIN
Drywall Nailing 11/3/2022 Approved AMY COLIN
Underground Mechanical 2/10/2023 Partial Approval OSVALDO PARAMO
Sewer 2/17/2023 Approved AMY COLIN
Underground Mechanical 3/9/2023 Approved AMY COLIN
ELECTRICAL-Final 4/19/2023 Approved AMY COLIN
PLUMBING-Final 4/19/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved AMY COLIN
Smoke Detectors 4/19/2023 Approved AMY COLIN
BUILDING-Rough-Frame 6/14/2023 Approved AMY COLIN
Final 6/14/2023 Partial Inspection AMY COLIN
HVAC-Final 6/14/2023 Approved AMY COLIN
Final 7/11/2023 OK to Issue CofO AMY COLIN